Jane with Mrs Seward as a 130 ton vessel arrives on the Petrogal Refinery site at Porto.
The 130 tonne vessel arrives at the Petrogal Refinery.
Work commences on the Kenfig viaduct on the M4 Extension South Wales, a beam lifting system, designed, supplied, and operated by Sparrows Contract Services postioned 160 pre-cast beams weighing 78 tons each on the viaduct.
Sparrow Contract Services specially designed beam lifting system.
The vessel arrives on site and the Sparrow designed lifting frame is fitted.
Sparrows Demag 650/800t capacity truck crane lifting a 204 tonne Main Fractioner at Pembroke Cracking Companys installation at Angle in Pembrokeshire, Tailing in is an American Hoist 9310 200t capacity crane.